Dry Area: 25 sqft
Wet Area: 9 sqft
This project involves a complete renovation of the common toilet floor to improve durability, waterproofing, and appearance. The existing WC and shower screen will first be carefully dismantled and removed to provide full access to the work area. The existing floor tiles and screed will then be hacked and disposed of to a depth of approximately 45–60mm, ensuring a clean and stable substrate for the new flooring system.
A 2-layer ARDEX Quickseal 104 waterproofing membrane will be professionally applied to protect the floor against water seepage and moisture damage. Where necessary, Davco Floor Screed ECO will be used to carry out 30–40mm floor screeding to achieve a level and even surface before tile installation.
New floor tiles will be installed using weber-E-MIX Tile Fix 303, a high-performance tile adhesive that provides excellent bonding strength and long-lasting durability. After the tiles are installed, all joints will be finished with AM50 normal tile grout to provide a clean, neat, and water-resistant finish.
Upon completion of the tiling works, the existing WC and shower screen will be reinstalled. If either item is found to be damaged or requires replacement, the supply and installation of new fixtures will be treated as a variation order at an additional cost. The scope also includes the repair of two door locks. Should replacement parts be required due to damage or wear, additional charges will apply.
This scope includes painting works for the entire house, including all walls and the ceilings of both the common toilet and master toilet. The paint and primer will be supplied by the client, while the contractor will provide all necessary manpower, tools, and supporting materials required to complete the works professionally.
Prior to painting, all defective wall surfaces will be prepared by applying putty to cracks, dents, and uneven areas, followed by thorough sanding to create a smooth and uniform finish. Proper surface preparation ensures better paint adhesion and a high-quality final appearance.
To protect the homeowner's belongings, the contractor will carefully cover and protect all furniture, flooring, fixtures, and other exposed surfaces before painting begins. Upon completion, all protective coverings will be removed, and the work area will be cleaned, leaving the property neat and ready for use.
The completed painting works will provide a refreshed, clean, and modern appearance while enhancing the overall durability and aesthetic value of the home.